Implementation Playbook · v1.0

Pilot-to-Scale
Implementation Playbook

A phased delivery schedule illustrating how a city moves from policy design through pilot launch to full corridor activation. All timelines are indicative and subject to procurement and regulatory approval.

12-Month Indicative Timeline
Reference deployment schedule · Subject to RFP/contract
Core Workstream
Technical Integration
Governance / Audit
Preparation / Setup
Workstream / Milestone M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12
Phase 1 — Policy Design & System Integration
Programme Goal Definition
Institutional Coordination
FASTag & UPI Integration
ICCC Integration
Policy Rule Configuration
Phase 2 — Pilot Launch
Public Communication Campaign
Corridor 1 Go-Live
Incentive Distribution — Wave 1
Phase 3 — Evaluation & Policy Adjustment
Pilot Metrics Review
Policy Parameter Adjustment
Independent Audit Review
Phase 4 — Expansion Planning
Corridor 2–4 Onboarding
Shared Mobility Integration
Expansion Evaluation Report

Key Deliverables by Phase

Phase 1 · M1–M3
Policy Design
  • Programme goals document
  • Integration specification
  • Policy rule v1.0
  • Audit framework
Phase 2 · M4–M6
Pilot Launch
  • Commuter communication pack
  • Corridor 1 live
  • First incentive batch
  • Baseline traffic data
Phase 3 · M7–M9
Evaluation
  • Pilot performance report
  • Policy adjustment memo
  • Independent audit report
  • Commuter feedback analysis
Phase 4 · M10–M12
Expansion
  • 3+ corridors activated
  • Shared mobility connected
  • Expansion decision report
  • Year-2 roadmap draft
Timeline Notice: This Gantt chart is an indicative design specification. Actual timelines, scope, and milestones are subject to government procurement processes, regulatory approvals, local infrastructure readiness, and contract terms. MTSAi does not claim delivery timelines in advance of a signed agreement.